Bucaramanga, Santander, Colombia

“La Ciudad de Los Parques” (“City of Parks”), Bucaramanga, Colombia, reused the EFCO HAND-E-FORM® system for the construction of the Multifunctional Stadium of Bucaramanga.

EFCO’s HAND-E-FORM® system helped the contractor pour 18 m (59′-0″) high columns.

HAND-E-FORM supported by HAND-E-SHORE was used to form the risers. The 35° incline of the risers proved the excellent load distribution capacity of the EFCO HAND-E-SHORE system.

The contractor found that EFCO is an excellent partner for their concrete projects; therefore, they have purchased the versatile EFCO systems.

One riser was formed every four days and eight transversal beams were formed per week.